Pharos-Tribune

Local News

November 9, 2007

Lewisburg bridge completion delayed

County recommending that INDOT deny contractor’s request for extension.

Residents and visitors of Lewisburg will have to wait up to seven months longer to cross the bridge into town over the Wabash River.

Jack Isom Construction, the contractor restoring the Lewisburg bridge, failed to complete the project on time, reportedly because of weather conditions, and has asked for an extension until June 30, 2008. The bridge was scheduled to be finished Oct. 31.

Cass County Engineer Jodi Coblentz informed the commissioners on Monday that the highway department is fighting to get the extension request denied because officials believe Jack Isom Construction did not take all possible measures to ensure the project was completed on time.

“They are still working, but it’s still the same slow crew that we’ve had all summer,” Coblentz told commissioners.

At the meeting, Commissioner Steve Kain asked about weather and if it was possible to complete the bridge this year.

“It’s not so much the weather,” Coblentz said. “It’s just they have so much to do.”

Isom has yet to provide a sample of the custom concrete balusters for the bridge railing. The design and material must match 1913 style and get approved. Coblentz said they have been waiting over a year, and a bridge with no railing cannot be used.

“Without the bridge rails we cannot let traffic over it,” Coblentz said.

The bridge requires more than 800 balusters, none of which are installed.

Isom Construction has completed the north portion of deck on the bridge and a majority of the underneath. A crew is pouring concrete for the south portion of deck this week.

The $2 million project is 75.6 percent complete, according to the most recent progress report.

The company’s primary reason for being behind schedule is high water levels, cold temperatures and snow.

“This severely limited our ability to perform pier reconstruction or temporary supports,” wrote Bill Isom in the request letter dated Oct. 26.

From Nov. 13, 2006, through June 4, Isom Construction only worked a handful of hours, according to the request letter from the contractor.

“I have two of the best foreman in the state working this project but because of the restrictions due to design, water levels, cold temperature and redesign that were not within our control, I am asking for an extension to the completion date,” Isom wrote.

Coblentz said she saw this coming.

“We knew they weren’t going to meet it, but their schedule said they were,” Coblentz said. “They just didn’t follow their schedule.”

The county sent a letter to the Indiana Department of Transportation explaining why the extension should not be granted. INDOT has yet to respond, according to Coblentz.

In the meantime, project supervisor Casey Lynch responded to Jack Isom Construction in a letter dated Nov. 5 stating the extension to the contract would not be granted at this time. Lynch, who is employed by both the county and INDOT as quality control, instructed Isom what to include if he resubmitted the request.

The company is expected to explain why the project was scheduled to begin Sept. 5, 2006, but no one showed up to work on it until 61 days later. The county also wants to know what measures will be taken to regain those days and complete the project in a timely manner.

Currently payment is being withheld until a “complete and realistic” work schedule is submitted. Also, Jack Isom Construction began incurring liquidated damages at a rate of $1,500 per day on Nov. 1, which will accumulate until an extension is granted.

INDOT is aware of the contractor’s request. As of Thursday morning, they had not responded.

Besides inconvenience to residents, the delay is increasing the cost of the project, which is a big concern, says Coblentz.

Restoring the bridge is paid for through 80 percent federal funds and 20 percent local bridge funds. Most engineering on the project was paid for with a transportation enhancement grant, which is used for historic bridges.

INDOT and the county will likely pass the extra expense along to Isom Construction, Coblentz said.

In September 2005, a portion of the 94-year-old span fell into the Wabash. The bridge is 452 feet long and has not been repaired since 1986. The restoration is designed to add at least 50 years of life to the bridge.

One of three

Engineers want to preserve the character of the 1913 bridge because of its historic significance.

“We’re restoring it to as close to as original 1913 as possible,” Coblentz said.

The Lewisburg bridge is the oldest of three Luten bridges remaining in the county and one of only 51 statewide. The other two are the old Cass Station Road Bridge over the Wabash, just west of the existing bridge on 600E, and the Third Street Bridge over the Eel River in Logansport.

The Luten arch was designed by Daniel Luten, an early 20th century bridge designer from Indiana who taught at Purdue University.

Coblentz said the Lewisburg bridge is endorsed by the National Landmark Historical Society, the National Registry of Historic Places and Historic Bridges of Indiana.

Kevin Lilly can be reached at (574) 732-5117, or via e-mail at kevin.lilly@pharostribune.com

Text Only | Photo Reprints
Local News
  • memorial Not forgotten

    A plaque in Mount Hope Cemetery near a flagpole dedicated to those from Logansport and Cass County who served in the World War reads: “Let those who come after see that these men shall not be forgotten.”

    May 28, 2012 1 Photo

  • LHS freshmen ace algebra ECA

    Logansport High School administrators were “ecstatic” last week over results from the statewide algebra I end-of-course assessment that showed passing marks for all the freshmen who took the exam.

    May 28, 2012

  • Logan man hands Indy 500 winner milk

    Logansport resident Dave Forgey remembers listening to the Indianapolis 500 on the radio as a kid while his cousins and siblings would gather for a picnic.

    May 28, 2012

  • 2012 Lewis Cass graduation

    May 27, 2012

  • Carlos Paul Leal Former LPD officer Leal turns himself in

    Former Logansport police officer Carlos Paul Leal was arrested Friday afternoon on charges of theft, and officials Saturday said the counts stem from two separate investigations.

    May 27, 2012 1 Photo

  • 9-1-1 dispatchers will soon be able to text

    Cass County dispatchers will be able to text callers starting this summer — a move that is reflective of where emergency communication services are heading nationwide.

    May 27, 2012

  • Anderson Tours1.JPG Andersons officials predict consistent demand for corn

    Farmers, elevator operators and other business associates joined local officials and community leaders to hear from the company’s president and its ethanol group president about industry progress since the plant was built.

    May 27, 2012 2 Photos

  • Former LPD officer arrested, accused of theft

    Former Logansport police officer Carlos Paul Leal was arrested Friday afternoon on two charges of theft, according to information obtained today by the Pharos-Tribune.

    May 26, 2012

  • No jail for driver in fatal hit-and-run

    A 25-year-old Logansport man admitted Thursday to leaving the scene of a deadly wreck last year, but he will not serve any time in jail as the result of a plea agreement.

    May 25, 2012

  • Board backs 51 percent spike in utility rates

    For Paul Hartman, the issue facing the Logansport Stormwater Management Board is pretty simple.

    May 25, 2012

Community Calendar
Loading…
Events by eviesays.com
Featured Ads
More pharostribune.com
Hyperlocal Search
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Popular Searches
Powered by Local.com
AP Video
Air Canada Plane Makes Emergency Landing Raw Video: 19 Dead in Qatar Shopping Mall Fire Beryl Makes Landfall on Florida Coast Service Dogs Help Wash. Soldiers Battling PTSD Raw Video: Heckler Bursts in on Blair Testimony Japan Farmers Plant, Seek Radiation-free Rice UN Blames Syrian Forces for Shelling Houla Raw Video: Gay Protest Blocked in Moscow Vatican in Chaos After Butler Arrested for Leaks Jimmy Carter Endorses Egypt's Election Results Biden Addresses West Point Graduating Class Dozens of Children Killed in New Syria Attack Raw Video: Activists Allege Massacre in Syria NJ Man Charged With Murder in Death of Patz Support, Fun for Kids of Fallen Soldiers at Camp Fugitive Penguin Caught, Returned to Aquarium 50 Years Later, Underground Fire Still Burning Light Show Transforms Sydney Opera House Raw Video: Unruly Passenger Restrained in Miami Raw Video: Robber Uses Drive-thru Window
Parade
Magazine

Click HERE to read all your Parade favorites including Hollywood Wire, Celebrity interviews and photo galleries, Food recipes and cooking tips, Games and lots more.
Poll

The U.S. Postal Service is scaling back hours at about 13,000 post offices across the country so that it can keep open about 3,700 post offices it had targeted for closing. Do you support this plan?

Yes
No
Not sure
     View Results

eEdition